South East Central Railway, being Nodal Railway for Incentive Module in IPAS, vide letter No.SECR/HQA/WS/Incentive/196 dated 26.08.2019 (copy enclosed), has made a reference to Railway Board, seeking necessary guidelines for payment of incentive to the staff of Workshops/ Production Units…..

No.AIRF/30                                                                                Dated: August 30, 2019

 

The Director,

Mechanical Engineering(P-1),

Railway Board,

New Delhi

Dear Sir,

Sub: Revision of Hourly Rate of Incentive Bonus and Bonus Factor of Workshops/PUs in respect of staff under CLW Pattern/GIS –Reg.

 Ref: Railway Board’s letter No.2018/M(W)/814/59 dated 09.08.2019 (RBE No.131/2019)

South East Central Railway, being Nodal Railway for Incentive Module in IPAS, vide letter No.SECR/HQA/WS/Incentive/196 dated 26.08.2019 (copy enclosed), has made a reference to Railway Board, seeking necessary guidelines for payment of incentive to the staff of Workshops/ Production Units.

You are, therefore, requested to issue necessary guidelines to South East Central Railway Administration for early payment of incentive to the staff of Workshops/ Production Units.

 

 

 

 

Encl: As above

 

Copy to: General Secretaries, all affiliated unions – for information.